The 2018 Mill & Overlay and Full Depth Reclamation Improvements Project will include the following roadways:

 
Picture2.jpg

Mill & Overlay

Circle Pines Road

Emily Road

Kelly Drive

Kelly Circle

Parkwood Drive (from Highland Scenic Road to Mountain Ash Drive)

Parkwood Court

Wedgewood Drive (East of Parkwood Drive)

Flintwood Drive

 

Full Depth Reclamation

College Road (from TH 371 to Cypress Drive)

 

Reconstruction

Cedars Scenic Road (from city limits to 1,000-feet east)

Baxter Drive (north of TH 210)

 

 

The City’s pavement management plan has identified each of these road segments for a mill and overlay, full depth reclamation or reconstruction as indicated above.

Feasibility Report


CONSTRUCTION

College Road
With the exception of a few punch list items, College Road is now complete.

Mill & Overlay (Residential Areas)
With the exception of a few punch list items, the residential areas are now complete.

Baxter Drive
Work on Baxter Drive began on September 17th.  The full depth reclamation (FDR) was completed this week as well as the new storm sewer.  Next week, crews will begin construction of the new curb & gutter.

Cedar Scenic Road
Construction is scheduled to begin on Cedar Scenic Road on Monday, September 24th.  The road will be closed and the detour will be in place by 6:00 AM.  Crews will begin removals and excavation for the subcut. 

It is estimate that the project will be completed in approximately 3 weeks.  We are hoping to have the construction completed and the road open by October 15th.

We appreciate your patience and are doing our best to have the project completed ahead of schedule.  If you have any questions or concerns, please feel free to contact us.

 Links for detours can be found below:

Baxter Drive Detour Route

Cedar Scenic Road Detour Route
 


For more information, call or email these representatives:

Chuck Rickart, Project Manager | (612) 360-1283 | crickart@wsbeng.com

Chris Sonmor, Project Engineer | (320) 241-9439 | csonmor@wsbeng.com

 

logos.PNG