The 2018 Mill & Overlay and Full Depth Reclamation Improvements Project will include the following roadways:

 
Picture2.jpg

Mill & Overlay

Circle Pines Road

Emily Road

Kelly Drive

Kelly Circle

Parkwood Drive (from Highland Scenic Road to Mountain Ash Drive)

Parkwood Court

Wedgewood Drive (East of Parkwood Drive)

Flintwood Drive

 

Full Depth Reclamation

College Road (from TH 371 to Cypress Drive)

 

Reconstruction

Cedars Scenic Road (from city limits to 1,000-feet east)

Baxter Drive (north of TH 210)

 

 

The City’s pavement management plan has identified each of these road segments for a mill and overlay, full depth reclamation or reconstruction as indicated above.

Feasibility Report


CONSTRUCTION

College Road
With the exception of a few punch list items, College Road is now complete.

 Mill & Overlay (Residential Areas)
With the exception of a few punch list items, the residential areas are now complete.

Baxter Drive
We had much improved weather through the week which allowed us to finally make some progress.  All of the grading has been completed as well as the new trail.  The street was paved on 10/19.  Next week, restoration (sod) will continue, the road will be striped and the signage will be installed.  Our hope is to have to road open by the end of the day on 10/26.

 We would like to remind everyone that even when no work is being done on Baxter Drive, the road remains closed to traffic.  It is illegal to move traffic control devices to gain access to closed streets.  Please do not use the closed portion of Baxter Drive until the construction is complete.

Baxter.jpg

Cedar Scenic Road
Crews have continued to work on Cedar Scenic Road.  The grading has been completed and the aggregate base has been placed.  The final shaping of the aggregate base will be done and the paving is expected to take place during the week of October 22nd.

Crews have been able to continue with the work on Cedar Scenic Road.  The muck excavation is now complete.  They have begun grading the road prepping for the placement of the aggregate base.  It is expected to be ready for the first lift of bituminous pavement the week of October 15th.  The road will continue to be closed.  Please follow the detour route.

We are expecting to have the road open by the end of the week of October 22nd.

We appreciate your patience during this project.  We are nearing completion.  We ask that you remain patient as we hope to open the remaining roads in the next week.  If you have any questions or concerns, please feel free to contact us.

The detour route for Cedar Scenic Road is shown below.


For more information, call or email these representatives:

Chuck Rickart, Project Manager | (612) 360-1283 | crickart@wsbeng.com

Chris Sonmor, Project Engineer | (320) 241-9439 | csonmor@wsbeng.com

 

logos.PNG